Long Term Construction Detours

Hello! I saw a post on “unpredictable” closures, but what of long-term closures? Chicago’s Western Ave at Belmont (3200 N. Western Ave, Chicago) just had its overpass bridge demolished and that segment of Western Ave will be reduced to a single lane more than 6 months (I believe). Is there anyway to indicate a semi-permanent closure or detour? Here are the anticipated closings:
The crumbling viaduct is over 50 years old, and taking it apart is expected to take six months.
During that time, traffic will be reduced to one lane in both directions. Once its down, two lanes in each direction will be open.
After 18 months, the viaduct will be replaced with a new intersection at Western, Belmont, and Clybourn Avenues.

The “one lane of traffic” is often congested with construction vehicles and a recommended detour route is in place with signage.
From Chicago’s Schedule of Closures.

Thanks,
Pradhan

In short, there is a difference between closures and construction hazards. At this time we have no way to indicate long term construction hazards, we can only fully close street segments. On a related note, as the travel speeds on those segments gets slower, Waze will see that and adjust routes accordingly.

Sent from my iPhone using Tapatalk

We have an editor that was on top of the Western Ave construction. We closed the bridge, I’ll check with the other State Mgr that was handling it. We will probably delete the center bridge lane since it is gone now.

And as citeman said, slow traffic thru the area will show up and should route you around the area.

Excellent. I love Waze and recommend it to everyone.