Road Closure Request - Athgarvan Road, Newbridge

Forum for requesting any unlocks, closures or fixes by a higher rank editor.
Please read "Posting Guidelines" before submitting your request.

Moderators: Unholy, davidg666, arthurohara

Road Closure Request - Athgarvan Road, Newbridge

Postby shane_meagher » Thu Feb 11, 2021 4:05 pm

Hi,

There is currently a road closure on Athgarvan Road, Newbridge from entrance to Supervalu to Lidl entrance. This corresponds to Phases 1 & 2 of the notification on Irish Water website.

nax8jq2fpab2a7vt58ai5l9j95xgmf3.jpg
Road Closure Phasing
(201.07 KiB) Downloaded 45 times


Road closures:

Phase 1: 10 February – 17 February; Entrance to Lidl carpark to Newbridge Retail Park. Access to carpark will be maintained throughout road closure.

Phase 2: 17 February – 25 February 2021; Newbridge Retail Park. Access to carpark will be maintained throughout road closure.

Phase 3: 26 February – 4 March 2021; Newbridge Retail Park to Dunnes Stores back exit. Access to this exit may be impacted over two nights.

Phase 4: 5 March – 8 March 2021; Dunnes Stores back exit to Cill Dara Business Park entrance. Access to Cill Dara Business Park will be maintained.

Phase 5: 9 March – 17 March 2021; Dunnes Stores back exit to Moorefield Park entrance. Access to Cill Dara Business Park will be maintained using other access road. Access to Moorefield Park estate will be maintained.

Phase 6: 18 March – 23 March 2021; Cill Dara Business Park to Newbridge Shopping Centre. Access to Moorefield Park and Newbridge Shopping Centre will be maintained

Stop/Go Shuttle System:

Phase 7: 24 March – 25 March 2021; Moorefield Park to Newbridge Shopping Centre entrance. Access to Moorefield Park and Newbridge Shopping Centre will be maintained.

Works will demobilize over the Easter period and the Athgarvan Road reopen between 27 March and 6 April. Works will resume on 6 April with stop/go shuttle system in place for the remaining phases.

Phase 7: 07 April – 09 April 2021; Moorefield Park to Newbridge Shopping Centre entrance. Access to Moorefield Park and Newbridge Shopping Centre will be maintained

The details of the remainder of the stop/go shuttle system are currently in draft and subject to further discussions and final agreement with the relevant roads authorities. We will endeavour to keep you updated as the project progresses


Permalink: https://waze.com/editor?env=row&lat=53. ... ,211890415

Reference: https://www.water.ie/projects-plans/new ... terupgrad/

Thank you in advance,
shane_meagher
 
Posts: 14
Joined: Mon Apr 10, 2017 2:04 am
Has thanked: 0 time
Been thanked: 2 times

Re: Road Closure Request - Athgarvan Road, Newbridge

Postby shane_meagher » Sat Feb 13, 2021 10:25 am

Yes, I think it reads that Phase 1 should end on 17th at 23:59 and Phase 2 start on 17th at 00:00 as there will be overlap.

Realistically though, the dates are already looking indicative as they have closed off both Phase 1 and Phase 2 sections as of Thursday evening, 11th.

Sent from my ONEPLUS A5010 using Tapatalk
shane_meagher
 
Posts: 14
Joined: Mon Apr 10, 2017 2:04 am
Has thanked: 0 time
Been thanked: 2 times

Re: Road Closure Request - Athgarvan Road, Newbridge

Postby shane_meagher » Sat Feb 13, 2021 4:12 pm

Will do. Thanks.

Sent from my ONEPLUS A5010 using Tapatalk
shane_meagher
 
Posts: 14
Joined: Mon Apr 10, 2017 2:04 am
Has thanked: 0 time
Been thanked: 2 times

Re: Road Closure Request - Athgarvan Road, Newbridge

Postby shane_meagher » Mon Feb 22, 2021 1:11 pm

Edit: Double posted
Last edited by shane_meagher on Mon Feb 22, 2021 2:34 pm, edited 1 time in total.
shane_meagher
 
Posts: 14
Joined: Mon Apr 10, 2017 2:04 am
Has thanked: 0 time
Been thanked: 2 times

Re: Road Closure Request - Athgarvan Road, Newbridge

Postby shane_meagher » Mon Feb 22, 2021 1:13 pm

@YanisKyr,

The next phase (3) is active now. Phase 1 has reopened so there is access to Cill Dara Industrial Estate from both ends.

Thanks,
Shane

Sent from my ONEPLUS A5010 using Tapatalk
shane_meagher
 
Posts: 14
Joined: Mon Apr 10, 2017 2:04 am
Has thanked: 0 time
Been thanked: 2 times

Re: Road Closure Request - Athgarvan Road, Newbridge

Postby shane_meagher » Mon Feb 22, 2021 2:36 pm

Ya that looks about right. Thanks.

Sent from my ONEPLUS A5010 using Tapatalk
shane_meagher
 
Posts: 14
Joined: Mon Apr 10, 2017 2:04 am
Has thanked: 0 time
Been thanked: 2 times

Re: Road Closure Request - Athgarvan Road, Newbridge

Postby shane_meagher » Mon Mar 01, 2021 9:10 pm

Hi @YanisKyr,

Phase 4, 5 & 6 are now active. Phase 1-3 have been reopened.

Works appear to be running ahead of the schedule provided originally.

Thanks.
shane_meagher
 
Posts: 14
Joined: Mon Apr 10, 2017 2:04 am
Has thanked: 0 time
Been thanked: 2 times

Re: Road Closure Request - Athgarvan Road, Newbridge

Postby YanisKyr » Sat Feb 13, 2021 8:49 am

Hey Shane, thanks for the very comprehensive post and sorry for only getting back to you now.

I closed the segments you linked for Phase 1 but I'm not sure how to proceed about scheduling the following phases. The article says Ph 1-6 will be 24/7 so shall we expire Ph1 at 23:59 and start Ph2 at 00:00? What do you think?

[ img ]
PL
Last edited by YanisKyr on Sat Feb 13, 2021 3:00 pm, edited 1 time in total.
[ img ] [ img ] [ img ]
CM for Ireland
YanisKyr
 
Posts: 504
Joined: Sat Dec 24, 2011 8:41 am
Location: Ashbourne, Ireland
Has thanked: 331 times
Been thanked: 99 times

Re: Road Closure Request - Athgarvan Road, Newbridge

Postby YanisKyr » Sat Feb 13, 2021 3:02 pm

So for the time being I have Ph1 expiring on 17 Feb and Ph2 expiring on 25 Feb. I'll hold off adding the subsequent closures in case the timeline becomes more fluid as they go. Keep us updated :)
[ img ] [ img ] [ img ]
CM for Ireland
YanisKyr
 
Posts: 504
Joined: Sat Dec 24, 2011 8:41 am
Location: Ashbourne, Ireland
Has thanked: 331 times
Been thanked: 99 times

Re: Road Closure Request - Athgarvan Road, Newbridge

Postby YanisKyr » Mon Feb 22, 2021 1:44 pm

Thanks for the heads-up Shane. So now I'm leaving Ph2 until 25 Feb 23:59, and adding Ph3 from now until 4 Mar 23:59.

Would you mind running an eye over the screenshot below and check if I have the phases correctly marked? (4 and 5 are smaller sections but we will use one segment in the editor)
[ img ]
[ img ] [ img ] [ img ]
CM for Ireland
YanisKyr
 
Posts: 504
Joined: Sat Dec 24, 2011 8:41 am
Location: Ashbourne, Ireland
Has thanked: 331 times
Been thanked: 99 times

Next

Return to Ireland Editor Requests

Who is online

Users browsing this forum: No registered users