Re: L5 Update: M50 S J6 ramp

Postby davidg666 » Tue Jul 26, 2016 2:25 pm

Hi Yanis,
YanisKyr wrote:Hi guys, I believe the ramp connection should be moved a good few hundred meters earlier. The actual 4th lane/exit lane is ongoing from J5 therefore also beneficial for drivers to choose the correct lane early. However the main reason is that the app waits until the "exit left", to give the next crucial direction (keep right/left) which comes at this point http://bit.ly/2aHabEK - only 100m before the actual split.

If it wasn't for the timing of the next instruction, I'd say that the positioning of the ramp instruction is OK, although the M50 junctions are a bit odd in that there's a continuous lane joining all entry and exit tamps.

Anyway, I don't see much harm in moving the ramp connection back a bit. I'm not sure about moving it a few hundred metres though maybe 100m or 200m at most.

I've lowered the locks around here (and on many other parts of the M50) to L3.

++David \ davidg666
Country manager and local champ for Ireland
AM for Dublin, Wicklow, Kilkenny, Wexford, Graiguenamanagh and Enniscorthy

[ img ]
davidg666
Waze Local Champs
Waze Local Champs
 
Posts: 974
Joined: Thu Jan 12, 2012 6:58 pm
Location: Wicklow, Ireland
Has thanked: 85 times
Been thanked: 208 times

L5 Update: M50 S J6 ramp  Topic is solved

Postby YanisKyr » Tue Jul 26, 2016 10:13 am

Hi guys, I believe the ramp connection should be moved a good few hundred meters earlier. The actual 4th lane/exit lane is ongoing from J5 therefore also beneficial for drivers to choose the correct lane early. However the main reason is that the app waits until the "exit left", to give the next crucial direction (keep right/left) which comes at this point http://bit.ly/2aHabEK - only 100m before the actual split.
YanisKyr
 
Posts: 468
Joined: Sat Dec 24, 2011 8:41 am
Location: Ashbourne, Ireland
Has thanked: 281 times
Been thanked: 87 times

Re: L5 Update: M50 S J6 ramp

Postby YanisKyr » Tue Jul 26, 2016 2:59 pm

Good stuff, thanks David. I'll make the change now, and see how it works out. Using that junction often lately :)
YanisKyr
 
Posts: 468
Joined: Sat Dec 24, 2011 8:41 am
Location: Ashbourne, Ireland
Has thanked: 281 times
Been thanked: 87 times


Return to Ireland Editor Requests

Who is online

Users browsing this forum: No registered users