3rd Street Tunnel Construction Project
So, there are dozens of URs coming up along Massachusetts NW, all the way from N Capitol over to 7th. These closures started on Sept 8, 2014 and will run through the end of 2016. The project has a website to detail the planned closures but from reading the press release, there will also be *As Needed* closures that are unscheduled.
To start, it appears that we need the following road closures submitted through 5/20/15 M-F 7am to midnight & Sat 8am to 6pm:
We are currently in Phase II of the project (see below). And for those that don't want to comb through the site, I can summarize. IT IS A MESS!
Thanks,
Russ...
--
http://3rdsttunnel.com/traffic/
Fact sheet
Site camera -- Get a glimpse of the mess before you go there
--
To start, it appears that we need the following road closures submitted through 5/20/15 M-F 7am to midnight & Sat 8am to 6pm:
- Mass Ave NW between 2nd and 5th
H St NW between 2nd and 5th
3rd St NW between H & K
We are currently in Phase II of the project (see below). And for those that don't want to comb through the site, I can summarize. IT IS A MESS!
Thanks,
Russ...
--
http://3rdsttunnel.com/traffic/
Fact sheet
Site camera -- Get a glimpse of the mess before you go there
--
- Phase I -- (June 10 – September 25, 2014) A new temporary traffic pattern will be put in place to allow crews to remove, relocate, and replace existing underground utilities along Mass Ave and H St, NW, between 3rd and 4th Streets. For the duration of Phase I, H St east and westbound
- Phase II -- (September 25 – February 6, 2015) During Phase II, crews will advance their work at the intersection of 3rd and H Street, which will be closed temporarily during this phase, and both vehicular and pedestrian traffic will be detoured around the area. Traffic traveling south bound on 3rd street will
- Phase III -- (February 6, 2015 – May 21, 2015) A new traffic pattern will reopen traffic to a new H Street alignment. Vehicles traveling westbound on H Street will be able to either continue westbound onto Mass Ave or continue southbound onto 3rd Street. For the duration of Phase III, H St
- Phase IV -- (May 21, 2015) Similar traffic pattern to phase III of construction. No additional lane closures.