During January we are going to upgrade the tile builder, in order to do that we will not release the map for ~4 days in each environment.
The planned timeline per environment is as follow:
- IL - Jan 5-9
- ROW - Jan 12-16
- NA - Jan 19-23
What would be the impact:
- No tile build during those days
- Jams will not be displayed for Beta users
- We will sync with the Beta community to gather feedback and make sure everything looks good
Thank you,
Ruben
During January we are going to upgrade the tile builder, in order to do that we will not release the map for ~4 days in each environment.
The planned timeline per environment is as follow:
- IL - Jan 5-9
- ROW - Jan 12-16
- NA - Jan 19-23
What would be the impact:
- No tile build during those days
- Jams will not be displayed for Beta users
- We will sync with the Beta community to gather feedback and make sure everything looks good
Thank you,
Ruben