Road Closure Request - Athgarvan Road, Newbridge
Hi,
There is currently a road closure on Athgarvan Road, Newbridge from entrance to Supervalu to Lidl entrance. This corresponds to Phases 1 & 2 of the notification on Irish Water website.
Reference: https://www.water.ie/projects-plans/new ... terupgrad/
Thank you in advance,
There is currently a road closure on Athgarvan Road, Newbridge from entrance to Supervalu to Lidl entrance. This corresponds to Phases 1 & 2 of the notification on Irish Water website.
Permalink: https://waze.com/editor?env=row&lat=53. ... ,211890415Road closures:
Phase 1: 10 February – 17 February; Entrance to Lidl carpark to Newbridge Retail Park. Access to carpark will be maintained throughout road closure.
Phase 2: 17 February – 25 February 2021; Newbridge Retail Park. Access to carpark will be maintained throughout road closure.
Phase 3: 26 February – 4 March 2021; Newbridge Retail Park to Dunnes Stores back exit. Access to this exit may be impacted over two nights.
Phase 4: 5 March – 8 March 2021; Dunnes Stores back exit to Cill Dara Business Park entrance. Access to Cill Dara Business Park will be maintained.
Phase 5: 9 March – 17 March 2021; Dunnes Stores back exit to Moorefield Park entrance. Access to Cill Dara Business Park will be maintained using other access road. Access to Moorefield Park estate will be maintained.
Phase 6: 18 March – 23 March 2021; Cill Dara Business Park to Newbridge Shopping Centre. Access to Moorefield Park and Newbridge Shopping Centre will be maintained
Stop/Go Shuttle System:
Phase 7: 24 March – 25 March 2021; Moorefield Park to Newbridge Shopping Centre entrance. Access to Moorefield Park and Newbridge Shopping Centre will be maintained.
Works will demobilize over the Easter period and the Athgarvan Road reopen between 27 March and 6 April. Works will resume on 6 April with stop/go shuttle system in place for the remaining phases.
Phase 7: 07 April – 09 April 2021; Moorefield Park to Newbridge Shopping Centre entrance. Access to Moorefield Park and Newbridge Shopping Centre will be maintained
The details of the remainder of the stop/go shuttle system are currently in draft and subject to further discussions and final agreement with the relevant roads authorities. We will endeavour to keep you updated as the project progresses
Reference: https://www.water.ie/projects-plans/new ... terupgrad/
Thank you in advance,
Re: Road Closure Request - Athgarvan Road, Newbridge