[COMPLETED] Middlegreen Rd bridge, Langley
Permalink
The old Middlegreen Road bridge has been removed as part of Crossrail works. The replacement bridge is scheduled for installation during Easter, reopening to traffic in late April 2013.
Network Rail press release
25/01/13: Segment ID 121767754 has been disconnected from both of its adjoining segments.
On completion of the bridge replacement works, reconnect this segment at both ends.
The old Middlegreen Road bridge has been removed as part of Crossrail works. The replacement bridge is scheduled for installation during Easter, reopening to traffic in late April 2013.
Network Rail press release
25/01/13: Segment ID 121767754 has been disconnected from both of its adjoining segments.
On completion of the bridge replacement works, reconnect this segment at both ends.
Re: [COMPLETED] Middlegreen Rd bridge, Langley