Per the Franklin County Engineer’s website, Norton Road will close at Johnson Road on June 17th for about 60 days to facilitate Roundabout Construction.

https://www.facebook.com/franklincountyengineer/photos/a.147482572123511/1087388438132915/?type=3&theater

https://www.waze.com/livemap?utm_campaign=waze_website&lat=39.89129941&lng=-83.15475583&zoom=17

Thanks. I have scheduled the closures at the intersection. We can build the roundabout on the map before it reopens.

Construction at this intersection has wrapped up and the road opened this morning. The roundabout is now in place. Standard single lane roundabout, maintains access to all four directions of Norton and Johnson.

The road has been re-opened. It may take about 24-48 hours before the roundabout shows up in the app though.