Urbana Ohio - Monument Square Roundabout Construction

(Urbana, OH) – On Monday, May 6, 2019, the City of Urbana’s contractor, R.B. Jergens Contractors, Inc., will start work on the planned improvements to the Monument Square Roundabout at the intersection of US Route 36 and US Route 68. This project includes safety improvements to the existing roundabout, additional lighting, and water main replacement work. In addition, this project also encompasses final resurfacing and restriping at the end of the project.

Project work will commence with the construction of the new truck apron around the base of the existing monument. Phase 1 of this work is anticipated to last approximately two weeks, and traffic will be maintained. However, delays are possible during the first phase. Phases 2-5 will involve the closure of one leg of the square at a time. For example, the northern leg (North Main Street) between Monument Square and East Court Street is planned to be closed first around May 20, 2019. Local detours and truck detours will be signed accordingly for each phase. Phase 6 will involve the milling and repaving of the finished improvements, and this work is anticipated to occur during the overnight hours later this fall.

Final project completion date is anticipated by October 31, 2019. Throughout the project, project updates will be posted to the city’s website: urbanaohio.com and on the city’s Facebook page. Businesses will be able to remain open as normal during the construction. Parking will be affected during the different phases of the project, but pedestrian access to businesses will be maintained.

Phase 1 from May 6, 2019 until May 19, 2019 - Roundabout Truck Apron Construction, traffic is maintained but delays may occur.

Hi, thanks for posting here about this! Will the road layout change at all in this? Could you provide other start and end dates of the closures here? We can schedule them in the map editor

I scheduled the closures based on the information on the urbanaohio.com website you provided. If you notice that the schedule changes, please post here to alert someone to look at it. With so many projects across the state, we’re likely to forget to keep checking on it. :oops:

For reference:
City’s project website
Permalink to Monument Square

Thank you very much for the information!

(Urbana, OH) – On Monday, May 20, 2019, the City of Urbana’s contractor, R.B. Jergens Contractors, Inc., will continue work on the planned improvements to the Monument Square Roundabout at the intersection of US Route 36 and US Route 68.

During the first phase of the project, a new truck apron around the base of the existing monument was installed. Phases 2-5 will involve the closure of one leg of the square at a time. The second phase starts on Monday, May 20, 2019, in the northern leg (North Main Street) between Monument Square and East Court Street, which will be closed for up to 5 weeks to allow for completion of this phase.

Thank you! We do have the northern leg closed as of 8:00am this morning. The closure is currently scheduled to end on June 24th.

Construction dates updates:

Phase 2 from May 20, 2019 until July 7, 2019 - North Leg Installation, 100 black of North Main Street from Monument Square to Court Street will be closed.

Phase 3 from July 8, 2019 until August 11, 2019 - East Leg Installation, 100 black of Scioto Street from Monument Square to Locust Street will be closed.

Phase 4 from August 12, 2019 until September 11, 2019 - South Leg Installation, 100 black of South Main Street from Monument Square to Market Street will be closed.

Phase 5 from September 12, 2019 until October 20, 2019 - West Leg Installation, 100 black of Miami Street from Monument Square to Walnut Street will be closed.

Phase 6 from October 21, 2019 until October 31, 2019 - Final project paving and milling (overnight), traffic is maintained.

I have updated the closures. Thanks for the info!

Construction dates updates:

Phase 3 from July 8, 2019 until August 15, 2019 - East Leg Installation, 100 black of Scioto Street from Monument Square to Locust Street will be closed.

Phase 4 from August 16, 2019 until September 11, 2019 - South Leg Installation, 100 black of South Main Street from Monument Square to Market Street will be closed.

Phase 5 from September 12, 2019 until October 20, 2019 - West Leg Installation, 100 black of Miami Street from Monument Square to Walnut Street will be closed.

Phase 6 from October 21, 2019 until October 31, 2019 - Final project paving and milling (overnight), traffic is maintained.

Phases 3 & 4 updated with new dates. Thanks!

Contractor construction dates updates:

Phase 4 from August 16, 2019 until September 23, 2019 - South Leg Installation, 100 block of South Main Street from Monument Square to Market Street will be closed.

Phase 5 from September 24, 2019 until October 27, 2019 - West Leg Installation, 100 block of Miami Street from Monument Square to Walnut Street will be closed.

Phase 6 from October 28, 2019 until November 6, 2019 - Final project paving and milling (overnight), traffic is maintained.

Thank you for the updates! I’ve updated the dates for the closures in the editor.

Construction date update:

Phase 4 from August 16, 2019 until September 23, 2019 - South Leg Installation, 100 block of South Main Street from Monument Square to Market Street will be closed.

Phase 5 from September 23, 2019 until October 27, 2019 - West Leg Installation, 100 block of Miami Street from Monument Square to Walnut Street will be closed.

Phase 6 from October 28, 2019 until November 6, 2019 - Final project paving and milling (overnight), traffic is maintained.

Thanks. I adjusted the start date for the west leg closure back one day.

Construction date update:

Phase 5 from September 23, 2019 until November 6, 2019 - West Leg Installation, 100 block of Miami Street from Monument Square to Walnut Street will be closed.

Phase 6 from October 27, 2019 until November 6, 2019 - Final project paving and milling (overnight), traffic is maintained.

Thank you for the update! I extended the closure for phase 5 through November 6th. For phase 6, it says traffic is maintained, so there is nothing to change.

Construction date update due to the weather delays:

Phase 5 from September 23, 2019 until November 8, 2019 - West Leg Installation, 100 block of Miami Street from Monument Square to Walnut Street will be closed.

All streets will reopen on or before November 9, 2019.

I extended the last closure through November 8th. Thanks!