Level5 Update: Queensland - Burpengary East (M1 - Bruce Hwy)

My Level: 2
Reason for request: Speed change long term roadworks.

Lane narrowing for new overpass. Expected completion early 2023 on Main Roads project page.
80 zone both ways. Receiving a few general reports and I’ve driven it a few times this week.

Permalink

Permalink

This section splits to 80 Level with southbound onramp.
Permalink

Unlocked

Thanks. Sorted.

Kyle

Thanks. Locked

My stuff up, marked wrong overpass. Need to revert to 100.
@BeastlyHaz has already dropped the correct one.

Can you provide a PL please so there’s no confusion? :slight_smile:

Just need to revert these back to 100. Was only 9pm but obviously I had a brain fade at the time.

https://www.waze.com/editor?env=row&lon=152.97989&lat=-27.14366&zoom=4&segments=326667874,186290705

https://www.waze.com/editor?env=row&lon=152.98204&lat=-27.14274&zoom=4&segments=197399251,90522377

https://www.waze.com/editor?env=row&lon=152.98219&lat=-27.14994&zoom=4&segments=344246952

First two links done.
Third no segments were highlighted when I opened it.

Be gentle with these highways please :smiley: