The OH 91 widden project is still ongoing. please update this area or unlock it so I can update. Thanks
Permalink
Hi rainlake,
Thanks for your concern and attempt to fix the map! Road closures can only be added by Level 3 editors and above. We will be more than happy to assist in adding the closure.
This is what we have on this as of now. http://www.mytwinsburg.com/177/Construction-Project-Updates
This project consists of a combination full depth reconstruction, widening and resurfacing of approximately 0.73 miles along SR91 (Darrow Road) from Post Road north through the Glenwood intersection. The project includes curbs, sidewalks, and a modern roundabout at the SR91 and Glenwood Drive intersection.
The Ohio Department of Transportation will be administering and performing all construction inspection for this project. This project has been awarded to Karvo Paving Company for $4,745,581.52 and will continue through summer of 2016.
Tentative Schedule:
Engineering will continue to post a traffic advisory every two weeks for planned work. Inclement weather will delay and extend schedule.
DONE • March 21st – Start excavation for widening on east side between Post and Glenwood (3 months)
DONE • March 21st – continue utility work in the vicinity of the intersection SR91/Glenwood (Limit movement onto EB Glenwood – WB traffic maintained)
DONE • Mid April – Temp Pavement SR91 at Glenwood Intersection
DONE • Late April close EB Glenwood mid June for pavement reconstruction of new intersection (Detour Posted using Liberty- Post Road-Darrow) Detour Map-Glenwood East
DONE • Mid June close WB Glenwood Early Aug for pavement reconstruction of new intersection (Detour Posted using Ravenna-Miktarian-Darrow) Detour Map-Glenwood West
DONE • CLOSE BOTH LEGS OF GLENWOOD 15 days (Aug)
DONE • Mid June working on West Side SR91 between Post and Glenwood (3 months)
I assume we are on this step? As you can see there isn’t much I can find to go off on this project.
• Install surface course of Asphalt, Pavement Markings and signage
• Complete restoration/landscaping
• Completion: November 2016
Can you help me out with where we should have the closure in place? Just the segment you provided in your Permalink? For how long? and E to W, W to E or both?
We can also work on the parking lot roads you made and explain why they are red, not showing on the map and get them connected to Darrow Rd.
If anyone else can find any more info on the closure feel free to add it. I just had a few minutes this morning and thought i’d give it a shot.
I found more here : http://www.mytwinsburg.com/175/Engineering-Division
Glenwood Drive EB/WB at Darrow Road remains closed. It is anticipated the intersection will reopen September 30th, weather permitting.
I will get that segment closed through the 30th.
I found more here : http://www.mytwinsburg.com/175/Engineering-Division
Glenwood Drive EB/WB at Darrow Road remains closed. It is anticipated the intersection will reopen September 30th, weather permitting.
Is it closed East and West of Darrow?